Project Updates
Maroubra Renovation
And the clients are in and enjoying their new home.
What a fantastic job Paul and the team have done in getting this job completed. Our photographer will be dropping by shortly to take some final pics, but as you can see this renovation and addition has turned out beautifully.
Drummond Road
A busy month has been had on this project. Although it has been a little wet with the heavy rain that hit us during July, the last week has seen demolition to the front deck and removal of the old sliding door. The new master bedroom and Ensuite is also starting to take shape which will soon be ready for internal sheeting and tiling to commence.
The garage roller door and cladding installation was completed, resulting in lock up of this space. With the new windows on-site the team was also in the position to remove the old and install the new into the current house which has added new life to the build.
The coming weeks will see the new power connected to the dwelling and demolition to the front room will commence to prepare for the front slab to go in.
Sylvania Duplex
With a lot of heavy rain impacting production towards the end of July, the last few days of the month has seen blue skies allowing us the chance to seal up both units and install the skylights into the bathroom in unit a.
The cladding also commenced to the back wall on Unit B, with the Scyon Stria selection coming up fantastic. Apart from a few flashings, it is exciting to see that Unit B is now watertight.
The windows have also been installed giving the team a clear run at finishing all the cladding on both units.
With rough in from all trades due to be completed this week, the next step is for the internal lining stage to begin. We are really looking forward to seeing the plasterboard sheets go up and watching the internal components start to take shape.